Concrete Pour Planning
Plan truck deliveries, crew needs, and pour schedules for concrete placements.
Truck Scheduling
Crew & Equipment
Pour Timing
Joints & Sections
Total Concrete Volume (cu yd)
Truck Capacity
8 cu yd (short load)
9 cu yd (standard)
10 cu yd (full load)
11 cu yd (overload permit)
Round Trip Time (minutes)
Plant to site and back
Unload Time per Truck (minutes)
Placement Method
Direct chute
Pump truck
Crane & bucket
Conveyor belt
Pour Start Time
Order Overage (%)
Extra for waste/spillage
Calculate Schedule
Concrete Volume (cu yd)
Pour Type
Slab on grade
Elevated slab/deck
Foundation/footings
Walls
Columns
Finish Type
Broom finish
Bull float only
Machine trowel
Stamped/decorative
Exposed aggregate
Target Placement Rate (cu yd/hr)
Site Access
Good - easy truck access
Moderate - some restrictions
Difficult - limited access
Calculate Crew Needs
Ambient Temperature (°F)
Relative Humidity (%)
Wind Speed (mph)
Mix Type
Standard mix
Accelerated (calcium chloride)
Retarded (hot weather)
Fly ash mix (slower)
Target Slump (inches)
3" (stiff - footings)
4" (standard)
5" (pump mix)
6" (flowable)
Slab Thickness (inches)
Calculate Timing Windows
Slab Length (ft)
Slab Width (ft)
Slab Thickness (inches)
Maximum Aggregate Size
1/2"
3/4"
1"
1-1/2"
Control Joint Method
Saw cut
Tooled (groover)
Zip strip / plastic
Joint Pattern
Standard grid
Offset/staggered
Custom pattern
Calculate Joint Layout
Results
Quick Reference
Typical Placement Rates
Slab on grade (pump): 20-35 cu yd/hr
Slab on grade (direct): 15-25 cu yd/hr
Elevated slab: 15-25 cu yd/hr
Walls: 10-20 cu yd/hr
Columns: 5-15 cu yd/hr
Footings: 20-40 cu yd/hr
Joint Spacing Guidelines (ACI 302.1R)
Rule of thumb: 2-3× slab thickness (in feet)
4" slab: 8-12 ft spacing
5" slab: 10-15 ft spacing
6" slab: 12-18 ft spacing
Panel aspect ratio: max 1.5:1
Saw cut depth: 1/4 to 1/3 slab thickness